Reconstruction of WIS 20 Interchange at I-94 in Racine County

The Wisconsin Department of Transportation (WisDOT) resumed reconstruction of the WIS 20 Interchange and I-94 Mainline in Racine County as part of the I-94 North-South Freeway Project, starting Thursday, March 12, 2015, with scheduled completion late fall 2015.

Current closures:

- Long term single lane closure on I-94 WEST (NB) at WIS 20 until late fall 2015. Two lanes will be open to traffic.

- Long term single lane closure on I-94 EAST (SB) at WIS 20 until late fall 2015. Two lanes will be open to traffic.

- Long term full closure of I-94 EAST (SB) exit ramp to WIS 20 until mid Summer 2015. Traffic can utilize County highway K exit from I-94 EAST (SB) and the West Frontage Road as detour route to access WIS 20.

- Long term full closure of WIS 20 entrance ramp to I-94 EAST (SB) until late fall 2015. Traffic can utilize the West Frontage Road and WIS 11 entrance ramp to I-94 EAST (SB) as detour route.

For detailed information on current and upcoming closures on the project, please refer to the Closures tab on the website.

WIS 20 Interchange Project Overview:

The WIS 20 Interchange reconstruction work scheduled for 2014 and 2015 includes:

  • I-94 WEST (NB) and I-94 EAST (SB) mainline at WIS 20
  • Entrance and exit ramps to and from I-94 WEST (NB) and I-94 EAST (SB)
  • I-94 WEST (NB) and I-94 EAST (SB) Bridges over WIS 20
  • County C bridge over I-94

Please click here for 2015 project overview.

Completed Work in 2014:

- County C Bridge over I-94.

- I-94 WEST (NB) lanes at WIS 20.

- I-94 WEST (NB) bridge over WIS 20.

- WIS 20 Interchange exit and entrance ramps to/from I-94 WEST (NB).

All closures are weather dependent and subject to change.

The project team thanks you for your patience and cooperation throughout this project.